TSPi Plan Summary: Form SUMP



Name
...





Date
...



Team
...

Instructor
...

Part/Level
...

Cycle
...


Product Size Plan Actual

Requirements pages (SRS)





Other text pages





High-level design pages (SDS)





Detailed design lines





Base LOC (B) (measured)





 Base LOC (B) (measured)





(Estimated) (Counted)

 Modified LOC (M)





(Estimated) (Counted)

 Added LOC (A)





(N-M) (T+B+D-R)

 Reused LOC (R)





(Estimated) (Counted)

Total New and Changed LOC (N)





(Estimated) (A+M)

Total LOC (T)





(N+B-M-D+R) (Measured)

Total new Reuse LOC





Estimated Object LOC (E)




Upper Prediction Interval (70%)




Lower Prediction Interval (70%)





Time in Phase (hours)

Plan

Actual

Actual %

 Management and miscellaneous







 Launch







 Strategy and planning







 Requirements







 System test plan







 Requirements inspection







 High-level design







 Integration test plan







 High-level design inspection







 Implementation Planning







 Detailed design







 Detailed design review







 Test development







 Detailed design inspection







 Code







 Code review







 Compile







 Code inspection







 Unit test







 Build and integration







 System test







 Documentation







 Postmortem







  Total







Total Time UPI (70%)





Total Time LPI (70%)






Defects Injected

Plan

Actual

Actual %

 Strategy and planning







 Requirements







 System test plan







 Requirements inspection







 High-level design







 Integration test plan







 High-level design inspection







 Detailed design







 Detailed design review







 Test development







 Detailed design inspection







 Code







 Code review







 Compile







 Code inspection







 Unit test







 Build and integration







 System test







  Total Development







Defects Removed

Plan

Actual

Actual %

 Strategy and planning







 Requirements







 System test plan







 Requirements inspection







 High-level design







 Integration test plan







 High-level design inspection







 Detailed design







 Detailed design review







 Test development







 Detailed design inspection







 Code







 Code review







 Compile







 Code inspection







 Unit test







 Build and integration







 System test







  Total Development